Beraban Luxury Lofts Construction Project Update: March 2025

image-05dcf332afc0935cb87ecf5691cb1a7ced2d5b85-1200x800-jpg

Overall Progress

The Beraban Luxury Loft project continues to make significant advancements, maintaining momentum across both Phase 1 and Phase 2. Notable developments include major structural reinforcements, the near completion of key foundational elements, and the commencement of upper-level framework installations. The focus remains on ensuring high-quality execution while adhering to the planned construction schedule.

Basement and Ground Floor Completion

image-554e2b9c00e3ef95d4c0988c3639c096f5f864ae-1200x800-jpg
  • Phase 1 basement work is now at 100% completion, with all structural elements—including footplates, pedestal columns, and retaining walls—finalized.
  • Phase 2 basement completion has increased to 67%, with significant advancements in footplates and pedestal columns. However, some delays in slab and retaining wall work are being addressed.
  • Ground floor construction has reached 65% completion, with formwork and slab casting progressing rapidly.
  • First-floor structural work is in motion, including column installations and reinforcements.
  • Room mock-up construction, which began in mid-March, is now underway for both studio and loft units, focusing on interior layouts and material selection.

Structural and Reinforcement Achievements

image-8ec79c42fa500b4e965c36ff384a0a2f304f1591-1200x800-jpg
  • Soldier pile and tie beam work for both phases is fully completed.
  • Excavation for Phase 2 is now 80% complete.
  • Basement slab work for Phase 1 has 100% completion, while Phase 2 has reached 72%.
  • Retaining wall installations have progressed to 80% for Phase 2, ensuring foundational stability.
  • First-floor formwork installation is in full swing, with reinforcement work extending to elevator shafts and key load-bearing columns.
  • Concrete injection applied to the STP wall has strengthened durability, with routine slump tests conducted to verify compliance with quality standards.

Quality and Safety Measures

image-51955ef00969e1c0e75da6dc4afb3a928cfb9943-1200x800-jpg

To uphold construction standards, the team continues to implement regular safety inspections and structural integrity checks before each development phase.

  • Concrete strength testing is ongoing to ensure material reliability.
  • Workforce training sessions on safety protocols have been expanded, focusing on efficiency and accident prevention.
  • On-site compliance audits have been reinforced, ensuring adherence to occupational health and safety regulations.

Upcoming Milestones

  • First-floor slab construction will be completed by mid-April, paving the way for second-floor framework installation.
  • By July 2025, the structural work is expected to reach the top floor, marking a significant milestone in the project timeline.

The construction team remains dedicated to delivering a high-quality, structurally sound development on schedule, ensuring that Beraban Luxury Loft meets the highest standards of excellence.